Build the forecast from the work items

  1. In Jira’s advanced search, use parent = WEB-140 to find direct children. Replace the example key with your epic key. Decide whether to include their subtasks.
  2. For each item, capture its original estimate, time spent, and remaining estimate in hours. Keep each row to its own time fields so a subtask contributes once. Use zero remaining for finished work.
  3. Add hours already logged to hours remaining. Subtract the original estimate to find the forecast difference for that item.

Jira’s Parent field reference · Jira time tracking

Find what is driving the overrun

A checkout form had a 12-hour estimate. The team has logged 15 hours and expects another 4. That puts it at 19 hours at completion, 7 hours over plan.

Another item is 1 hour under plan, so the comparable epic total is 6 hours over. Look at the largest positive differences on individual items before discussing the epic total. They show where a smaller scope, a changed approach, or a new estimate would matter most.

Try the checkout example

Report how much of the epic is covered

Compare the same items on both sides. Include an item in the plan-versus-forecast total when it has an original estimate and a usable forecast. If 3 of 5 items qualify, say “6 hours over plan across 3 of 5 items” and list the two gaps.

Recheck stale remaining estimates with the team before treating the forecast as current. If the team estimates in story points, keep the hours forecast separate. Story points and hours measure different things.

Find the estimates missing from your forecast